See below key dates for the future airport project
Key Dates | Activities |
October 2011 – July 2012 | Demolition of top two floors of arrivals terminal |
February 2014 | Planning permission given for the removal of airport arrivals terminal |
July 2016 | Jersey Airport Master Plan publicly launched |
March 2017 | Integrated Terminal concept developed |
August 2017 | Corgan Peer Review confirms Integrated Terminal approach as best solution for Jersey |
October 2017 | PoJ Board Endorse Integrated Terminal |
November 2017 | Detailed design phase commences and public launch of Integrated Terminal |
December 2017 | Planning Application to be submitted for Integrated Terminal |
April 2018 | Planning Approval granted |
November 2018 | Phase 1 start on site |
December 2019 | Phase 1 complete and transfer Departures upstairs |
January 2020 | Phase 2 start on site |
December 2020 | Phase 2 complete and transfer Arrivals to ground floor |
Mid – 2021 | Complete removal of old Arrivals facilities |